Right Bank Foundation Enhancements
Once built, Site C will be a source of clean, reliable and affordable electricity in B.C. for more than 100 years. The engineering process that has been followed throughout the entire project is consistent with international best practices and the highest safety standards and has been reviewed by the independent Site C Technical Advisory Board.
We're implementing safety measures, reviewed and endorsed by two international experts, to ensure the right bank structures are safe over the long operating life of Site C.
Project Status Dashboard
Project Status Dashboard
To report on project status, we use a dashboard system where key Site C project areas are classified as red (at risk), amber (moderate issues) or green (on target). This dashboard is updated quarterly.
Site C Employment Statistics – March 2021
The total project workforce number increased in March with an increase of 444 workers for a total of 4,321. The total BC residency percentage remained at 73% in March. The apprentice number increased to 143. The Indigenous number saw an increase from 300 in February to 346 in March. The number of women increased by 37 for a total of 474.
Site C Employment Statistics - February 2021
The latest employment statistics show that there were 3,877 total workers on the Site C project in February 2021. Of the total workers, 2,840 were from British Columbia, or 73%. There were 767 workers on site from the Peace River Regional District – that's 24% of the construction and non-construction contractor's workforce.
Site C Employment Statistics - January 2021
Site C Employment Statistics - December 2020
The latest employment statistics show that there were 4,428 total workers on the Site C project in December 2020. Of the total workers, 3,173 were from British Columbia, or 72%. There were 880 workers on site from the Peace River Regional District — that’s 24% of the construction and non-construction contractor’s workforce.