Public advisory: Geotechnical investigations begin in Hudson’s Hope

Starting next week, BC Hydro will be conducting geotechnical investigations in various places throughout Hudson’s Hope. The purpose of this work is to install and commission groundwater monitoring wells.

We will be drilling small test holes at groundwater sample sites in different locations. Crews will be at each site for approximately two to three days.

Investigations, tests and installations of groundwater monitoring wells will continue until the end of October.

What to expect

  • There will be increased noise and vibration from drilling and hydrovac trucks. Noise levels will be similar to construction noise.
  • Traffic control personnel and signage will be in place.
  • Work is expected to occur 7 am – 7 pm from Monday to Saturday and 10 am – 7 pm on Sunday.
  • No interruption in utility services will result from this work.